Judge Rules Against Data Center Developer in Jessup Zoning Dispute

Lackawanna County judge denies appeal in Jessup data center case

The dispute over a proposed data center in Jessup has taken another turn, as a recent court decision has upheld the borough’s authority to deny the project. This comes after a prolonged legal battle initiated by the developer, who sought to overturn a previous rejection of their plans.

Breaker Street Associates LLC, based in Conshohocken, had their proposal to build a six-building data center campus on more than 200 acres in Jessup’s Breaker and Hill streets denied by the local planning commission last year. In response, the company appealed the decision, arguing that the borough failed to adhere to procedural requirements outlined in the Pennsylvania Municipal Planning Code.

Despite the developer’s contention that Jessup did not provide a timely written decision, Lackawanna County Judge Terrence R. Nealon ruled against Breaker Street on October 22, maintaining that the borough acted within its rights. According to court records, Nealon noted that Breaker Street had voluntarily resubmitted its plans twice, which reset the decision timeline under the planning code.

Jessup Council President Gregg Betti expressed satisfaction with the ruling, stating, “We’re obviously pleased with the outcome. We feel that we’re in the right.” However, Breaker Street’s attorneys, Richard Williams and Kevin Walsh Jr., have not commented on the decision.

The Past Year

Initially, Breaker Street submitted its application on June 11, 2025, to develop the data center, complete with an electrical switchyard and substation. On June 24, 2025, the planning commission denied the application, citing its location within a residential zone where data centers are not allowed. The Lackawanna County Regional Planning Commission also had reservations about the proposal.

In response to these issues, Breaker Street resubmitted revised plans on July 23, 2025, and October 2, 2025. Despite these efforts, the commission issued another denial on October 17, 2025, pointing out seven specific deficiencies in the application.

Breaker Street maintained that the planning commission’s decisions regarding their applications were not specific enough, arguing that this should result in the project being “deemed approved.” Judge Nealon, however, explained that the resubmissions introduced significant changes, effectively restarting the 90-day decision period.

Problems from the Beginning

From the outset, Breaker Street faced numerous challenges with their application. Both Jessup and Lackawanna County identified significant omissions, including the absence of a traffic study, erosion/sediment and stormwater management plans, and necessary utility company confirmations.

Additionally, the proposed construction included areas not zoned for data centers, such as residential zones slated for the switchyard and substation. Other issues included insufficient details on tree species for planting, inadequate parking information, and the lack of exterior building designs.