Texas Developer Sues Phoenix for $54 Million Over Data Center Zoning Rules

When a city changes its zoning rules, who pays the price? A Texas developer is now asking a Phoenix court to answer that question — to the tune of more than $54 million.

A company called West Buckeye Road LP (WBR) is suing the city of Phoenix after new regulations targeting data centers upended its construction plans. The dispute is testing the boundaries of a nearly two-decade-old Arizona property rights law and could set a significant precedent for how cities manage the booming data center industry.

What Happened

WBR says it purchased industrial land in Phoenix in 2021 and spent millions of dollars preparing the site for a data center. Then, in 2025, Phoenix adopted a new zoning ordinance requiring special permits for data centers operating within city limits. According to WBR, complying with the new rules — which include purchasing advanced cooling equipment and soundproofing panels — added millions in unexpected costs and significantly reduced the property’s value.

The developer is seeking more than $54 million in compensation, arguing the city’s new rules unfairly burdened a project that was already underway.

The Legal Claims

WBR is pursuing two separate legal arguments. The first relies on Proposition 207, Arizona’s Private Property Rights Protection Act, which voters passed in 2006. The law requires state and local governments to compensate property owners when a new land use regulation reduces their property’s value. However, the law does carve out exceptions for regulations designed to protect public health — including fire codes, building standards, and waste management rules.

WBR’s second claim argued that Phoenix’s own data center ordinance entitled the developer to sue the city directly for compensation. A Maricopa County Superior Court judge rejected that argument earlier this month, ruling that nothing in the city ordinance gives developers the legal right to bring such a lawsuit.

Posting on X, Phoenix Mayor Kate Gallego hailed the decision as a partial victory for the city.

But the fight is far from over. WBR’s claim under Proposition 207 is still alive, and the judge has scheduled a full evidentiary hearing for November 17. To have that claim dismissed as well, Phoenix will need to demonstrate that its data center ordinance was enacted to protect public health.

Why Data Centers Are Under Scrutiny

The lawsuit arrives as Arizona grapples with the sweeping demands the data center industry is placing on local infrastructure. Reporting by Taylor Griffith has documented how Arizona utilities are scrambling to expand the power grid at a pace that may be unprecedented in the state’s recent history — driven almost entirely by new data centers. Meanwhile, Greg Hahne has reported that Arizona could increasingly rely on natural gas as facilities demand ever-greater amounts of electricity.

Water use is also a concern. Alex Hager reported that while data centers drive up water demand, the impact is indirect — the facilities use relatively little water on site, but the power plants generating their electricity consume substantial amounts.

Beyond infrastructure, the education sector is also feeling the AI wave. ASU has said AI agents will become a critical partner in students’ careers, signaling how deeply the technology underpinning data centers is reshaping everyday life.

On the political front, Camryn Sanchez has reported on Arizona’s competitive CD1 congressional race, where voters face a stark choice between a Trump-endorsed Republican and a Democrat — a contest taking place amid all these unresolved questions about the state’s growth and resources.

For now, the outcome of WBR’s lawsuit hinges on a single question the court will take up in November: Is Phoenix’s data center ordinance truly a public health measure — or did it cross a legal line by reducing a property owner’s rights without fair compensation?